GEM-4C 558 -4%
GPT-61S 555 -3.8%
CL-SN55 553 -3.8%
CL-OP55 551 -4%
GPT-61TERR 547 -3.5%
GEM-4CM 546 -4%
CL-OP55EH 542 -3.9%
GPT-61SOLXH 541 -3.6%
GPT-61SOLH 527 -3.7%
CL-SN55XH 523 -3.5%
GEM-4CL 520 -3.9%
GPT-61TERRXH 507 -3.4%
CL-OP55H 506 -4%
GPT-61SOLM 500 -3.5%
KIMI-K31P 499 -3.5%
GEM-4AR 498 -3.9%
GPT-61TERRH 490 -3.2%
CL-OP55M 483 -3.6%
MUSE-WONDFUL 479 -3.8%
CL-SN55H 467 -3.3%
CL-HK55 463 -2.9%
GPT-61TERRM 462 -3.1%
GPT-6A 451 -4.7%
MUSE-WOND 451 -3.6%
CL-HK55XH 450 -3%
GPT-6ASTRXH 440 -4.8%
GROK-47 440 -3.1%
GROK-47H 438 -2.9%
GPT-6ASTRH 437 -4.8%
DSK-V-340615 436 -2.9%
QWEN-38X 428 -2.9%
GPT-61SOLL 423 -3.2%
GLM-53 420 -3%
MIMO-V26P 420 -2.6%
CL-HK55H 419 -2.8%
LING-31F1019 417 -2.6%
GEM-38F 416 -2.8%
GPT-6ASTRM 415 -4.6%
MMAX-M31F 414 -2.8%
GEM-38FM 412 -2.8%
GPT-61TERRNO 411 -2.8%
GROK-47L 410 -2.8%
DSK-V-3E48BD 410 -2.6%
GPT-6L 407 -2.6%
GLM-53F 407 -2.6%
STEP-5 405 -2.6%
CL-FABL51XH 403 -4.7%
GPT-61TERRL 403 -2.9%
MIMO-V26F 401 -2.4%
CL-FABL51 399 -4.5%
CL-SN55M 395 -2.9%
CL-OP55L 393 -3.4%
MIST-LARG4 390 -2.7%
CL-FABL51H 386 -4.5%
CL-HK55M 386 -2.3%
GPT-6LUNAXH 377 -2.6%
MUSE-SPAROPE 375 -2.6%
MIST-LARG4M 371 -2.4%
DSK-V4P 365 -2.4%
GPT-6LUNAH 365 -2.1%
GLM-53L 364 -2.4%
CL-SN55L 362 -2.7%
GEM-38FL 361 -2.4%
GPT-6ASTRL 359 -4.5%
CL-FABL51M 359 -4.5%
QWEN-827B 349 -2.2%
CL-HK55L 347 -2%
MMAX-M3 345 -2%
GPT-6LUNAM 344 -2.3%
DSK-V-02811D 344 -2%
K2-HORI375BA 342 -2%
REFL-BEAM 338 -2%
QWEN-827BM 332 -1.8%
CL-FABL51L 329 -4.4%
QWEN-827BL 320 -1.8%
NEMO-35SUPEV 313 -1.9%
INKL 295 -1.7%
NVID-NEMO3UL 295 -1.3%
GEM-35FLITE 295 -1.3%
GPT-6LUNAL 287 -1.4%
GPT-6LUNANON 286 -1%
NANB-333B 285 -2.7%
QWEN-827BNON 282 -1.4%
COMM-APLUS 266 -1.1%
MUSE-GLIM 263 -1.1%
NEMO-35LIGH 261 -0.8%
GRAN-428B 258 -0.8%
MIST-SMAL4 252 -0.4%
INKL-SM 235 -2.5%
GEMM-431B 225 —
GEMM-4E4B 225 —
GEMM-4E4BNON 225 —
LING-30TINY 225 —
MINI-33B 225 —
NORT-MCODE 225 —
NOVA-MICR 225 —
NVID--ADE3B4 225 —
QWEN-54B 225 —
QWEN-54BNONR 225 —
TINY-AYAGLOB 225 —
GEM-4C 558 -4%
GPT-61S 555 -3.8%
CL-SN55 553 -3.8%
CL-OP55 551 -4%
GPT-61TERR 547 -3.5%
GEM-4CM 546 -4%
CL-OP55EH 542 -3.9%
GPT-61SOLXH 541 -3.6%
GPT-61SOLH 527 -3.7%
CL-SN55XH 523 -3.5%
GEM-4CL 520 -3.9%
GPT-61TERRXH 507 -3.4%
CL-OP55H 506 -4%
GPT-61SOLM 500 -3.5%
KIMI-K31P 499 -3.5%
GEM-4AR 498 -3.9%
GPT-61TERRH 490 -3.2%
CL-OP55M 483 -3.6%
MUSE-WONDFUL 479 -3.8%
CL-SN55H 467 -3.3%
CL-HK55 463 -2.9%
GPT-61TERRM 462 -3.1%
GPT-6A 451 -4.7%
MUSE-WOND 451 -3.6%
CL-HK55XH 450 -3%
GPT-6ASTRXH 440 -4.8%
GROK-47 440 -3.1%
GROK-47H 438 -2.9%
GPT-6ASTRH 437 -4.8%
DSK-V-340615 436 -2.9%
QWEN-38X 428 -2.9%
GPT-61SOLL 423 -3.2%
GLM-53 420 -3%
MIMO-V26P 420 -2.6%
CL-HK55H 419 -2.8%
LING-31F1019 417 -2.6%
GEM-38F 416 -2.8%
GPT-6ASTRM 415 -4.6%
MMAX-M31F 414 -2.8%
GEM-38FM 412 -2.8%
GPT-61TERRNO 411 -2.8%
GROK-47L 410 -2.8%
DSK-V-3E48BD 410 -2.6%
GPT-6L 407 -2.6%
GLM-53F 407 -2.6%
STEP-5 405 -2.6%
CL-FABL51XH 403 -4.7%
GPT-61TERRL 403 -2.9%
MIMO-V26F 401 -2.4%
CL-FABL51 399 -4.5%
CL-SN55M 395 -2.9%
CL-OP55L 393 -3.4%
MIST-LARG4 390 -2.7%
CL-FABL51H 386 -4.5%
CL-HK55M 386 -2.3%
GPT-6LUNAXH 377 -2.6%
MUSE-SPAROPE 375 -2.6%
MIST-LARG4M 371 -2.4%
DSK-V4P 365 -2.4%
GPT-6LUNAH 365 -2.1%
GLM-53L 364 -2.4%
CL-SN55L 362 -2.7%
GEM-38FL 361 -2.4%
GPT-6ASTRL 359 -4.5%
CL-FABL51M 359 -4.5%
QWEN-827B 349 -2.2%
CL-HK55L 347 -2%
MMAX-M3 345 -2%
GPT-6LUNAM 344 -2.3%
DSK-V-02811D 344 -2%
K2-HORI375BA 342 -2%
REFL-BEAM 338 -2%
QWEN-827BM 332 -1.8%
CL-FABL51L 329 -4.4%
QWEN-827BL 320 -1.8%
NEMO-35SUPEV 313 -1.9%
INKL 295 -1.7%
NVID-NEMO3UL 295 -1.3%
GEM-35FLITE 295 -1.3%
GPT-6LUNAL 287 -1.4%
GPT-6LUNANON 286 -1%
NANB-333B 285 -2.7%
QWEN-827BNON 282 -1.4%
COMM-APLUS 266 -1.1%
MUSE-GLIM 263 -1.1%
NEMO-35LIGH 261 -0.8%
GRAN-428B 258 -0.8%
MIST-SMAL4 252 -0.4%
INKL-SM 235 -2.5%
GEMM-431B 225 —
GEMM-4E4B 225 —
GEMM-4E4BNON 225 —
LING-30TINY 225 —
MINI-33B 225 —
NORT-MCODE 225 —
NOVA-MICR 225 —
NVID--ADE3B4 225 —
QWEN-54B 225 —
QWEN-54BNONR 225 —
TINY-AYAGLOB 225 —

Delayed ticker data. Last calculated 5 Nov 2026, 11:04 pm Sydney time.

← Back to feed

61GW of AI Data Center Capacity Is Phantom: Sightline Finds Only 40% of Announced Projects Will Survive

The AI infrastructure narrative runs on announced gigawatts. Microsoft’s $80B. Oracle and OpenAI’s $15B Vantage partnership. Google’s multiyear TPU commitments. The numbers are real. The capacity they imply is not.

Sightline Climate, which tracks data center project pipelines, has assessed 710 projects totalling 102.3GW of announced capacity through 2030. Only 40.8GW of that meets its threshold as derisked — projects with secured grid interconnection, resolved permitting, and committed financing. The remaining 61.5GW, roughly 60% of what has been announced, faces material risk of delay or cancellation.

The New Bottleneck

For two years the binding constraint on AI infrastructure was chips: NVIDIA could not produce H100s fast enough, then GB200s. That period is ending. TSMC capacity has scaled. NVIDIA’s Vera Rubin production is in sight. CoreWeave and hyperscalers have contracted enough silicon.

The constraint that replaced it cannot be solved with a fab expansion or a supply chain deal. Data Center Watch counted at least 48 US data center projects blocked or delayed in 2025 — each one a claim on land, power grid access, substations, cooling infrastructure, permits, construction labour, and local political consent. Sightline estimates that 30% to 50% of large projects slated for 2026 could be delayed because of power constraints, equipment shortages, and local opposition.

MISO, the grid operator covering the Midwest and parts of the South, expects peak load to reach 163GW by 2035, up 35% from its 2025 peak of 121GW, driven primarily by data center development. That 42GW of new load is looking for grid connections that utilities are building on decade-long timescales.

What Derisked Looks Like

A derisked project has cleared the specific barriers that kill the rest:

  • Grid interconnection: Formal agreement with the utility, assigned substation capacity. The average wait time in the PJM queue — which covers the mid-Atlantic and parts of the Midwest — now exceeds three years for large loads.
  • Permits: Environmental, zoning, and local approvals in hand. Northern Virginia, the largest data center market in the world, has slowed significantly as Loudoun County and neighbouring jurisdictions tighten approvals.
  • Financing: Committed construction capital, not just letters of intent. Investment-grade debt like CoreWeave’s $8.5B loan is distinct from announced equity pipelines.

Projects that do not have all three remain in the announced category. Sightline’s methodology treats signed LOIs, capacity announcements, and land acquisitions as announced, not derisked.

The Announced-to-Real Conversion Rate

The gap has structural causes, not just temporary delays. Utility interconnection queues function as first-come, first-served queues that reward speed of application over seriousness of project. Speculative developers file early to hold position, inflating the announced pipeline. Many never build. Sightline estimates that the conversion rate from announced to operational capacity in the AI data center sector is running below 50%.

That figure has significant implications for anyone pricing AI infrastructure access in the 2027-2030 window. The announced capacity would suggest comfortable supply. The derisked capacity suggests something closer to a crunch.

What Changes the Math

Several interventions are in progress. The US government’s nuclear financing initiative is adding 5GW of existing nuclear output to the grid at low cost — material at the margin but not transformative. Some data center operators are pursuing co-location directly on power generation sites, bypassing the interconnection queue. Others are moving to markets with faster permitting: Texas, Arizona, parts of the Gulf Coast.

The structural constraint — that a data center is a coordinated claim on multiple scarce systems simultaneously — does not disappear with any single fix. At 102GW announced and 41GW viable, the gap is the story.

Key Numbers

MetricFigure
Total announced capacity (2030)102.3 GW
Derisked capacity40.8 GW
Capacity at risk61.5 GW (60.1%)
US projects blocked/delayed in 202548 (Data Center Watch)
2026 large projects at delay risk30–50% (Sightline estimate)
MISO projected load growth to 2035+42 GW (35%)